ISSUES & DELAYS
3 active · 5 resolved
Every issue tied to a milestone and a recovery plan.
OPEN
2#142medium
Cement supplier delay
Lucky Cement notified 36 hr delay on next 800-bag tranche for the C4 core pour. Backup: Bestway, 2-day lead time. Recovery plan filed.
supplier·Adnan Siddiqui·Wed·+2d impact
#138medium
LDA inspection rescheduled
LDA moved the G–L3 structure inspection from Oct 1 to Oct 2. No critical-path impact.
inspection·Adnan Siddiqui·Mon·+1d impact
IN PROGRESS
1#141low
Generator North runtime anomaly
Runtime 18% above baseline this week with no GPS movement to explain load. Inspecting Friday.
equipment·Adnan Siddiqui·Tue
RESOLVED
5#130low
Rebar shipment partial accept
4 of 12 tons short on weight; replacement delivered next day.
supplier·Adnan Siddiqui·Apr 19
#124low
Crane operator certification renew
Renewed and on file.
safety·Rashid Ali·Apr 12
#118medium
Power outage Apr 4 — 3hr
LESCO grid; generators picked up load. No work-time lost.
equipment·Adnan Siddiqui·Apr 4
#112medium
Heat-stress incident
One worker treated; staggered shifts implemented.
safety·Rashid Ali·Mar 28
#107low
Mason rate dispute (arcade crew)
Arcade arch masons renegotiated per-bay rate; agreement signed.
labor·Adnan Siddiqui·Mar 20