Mughal Bazaar/Issues
ISSUES & DELAYS

3 active · 5 resolved

Every issue tied to a milestone and a recovery plan.

OPEN

2
#142medium

Cement supplier delay

Lucky Cement notified 36 hr delay on next 800-bag tranche for the C4 core pour. Backup: Bestway, 2-day lead time. Recovery plan filed.

supplier·Adnan Siddiqui·Wed·+2d impact
#138medium

LDA inspection rescheduled

LDA moved the G–L3 structure inspection from Oct 1 to Oct 2. No critical-path impact.

inspection·Adnan Siddiqui·Mon·+1d impact

IN PROGRESS

1
#141low

Generator North runtime anomaly

Runtime 18% above baseline this week with no GPS movement to explain load. Inspecting Friday.

equipment·Adnan Siddiqui·Tue

RESOLVED

5
#130low

Rebar shipment partial accept

4 of 12 tons short on weight; replacement delivered next day.

supplier·Adnan Siddiqui·Apr 19
#124low

Crane operator certification renew

Renewed and on file.

safety·Rashid Ali·Apr 12
#118medium

Power outage Apr 4 — 3hr

LESCO grid; generators picked up load. No work-time lost.

equipment·Adnan Siddiqui·Apr 4
#112medium

Heat-stress incident

One worker treated; staggered shifts implemented.

safety·Rashid Ali·Mar 28
#107low

Mason rate dispute (arcade crew)

Arcade arch masons renegotiated per-bay rate; agreement signed.

labor·Adnan Siddiqui·Mar 20