PREDICTIVE FORECAST · MAX
Cost-at-completion + slip detection
Updated daily from burn-rate, dependency, and weather models. Click any slip prediction below for the AI recovery plan.
BUDGET
PKR 2.60B
approved
SPENT
PKR 849.0M
33% of budget
FORECAST
PKR 2.62B
at completion
VARIANCE
+0.88%
vs. budget
SPEND CURVE · 11 MONTHS
Planned vs. actual vs. forecast (PKR M)
PlannedActualForecast
AI · SLIP DETECTION
4 predictions across the critical path
Click any row for the full forecast distribution and recovery plan.
- #10Level 1 Gallery Slab+2 days91% confTarget May 31, 2026 → forecast May 31, 2026 – Jun 2, 2026C2 gallery rebar pace 4% behindweekend manpower variance
- #12Central Court C4 Core+7 days78% confTarget Jun 8, 2026 → forecast Jun 10, 2026 – Jun 15, 2026cement supplier delay #142backup supplier 4-hr lead
- #13Level 2 Slab · Prayer Halls & Food Court+4 days84% confTarget Jul 25, 2026 → forecast Jul 25, 2026 – Jul 29, 2026upstream C4 core slip
- #16LDA Structure Inspection (G–L3)99% confTarget Oct 2, 2026 → forecast Oct 2, 2026 – Oct 2, 2026regulator-confirmed date