Mughal Bazaar/Daily Log
DAILY LOG

31 entries · 31 days

PM-authored site log. Switch views, search, filter. Click any day for the full entry.

DAYS LOGGED
31
last 31 days
MAN-HOURS
33.1K
cumulative
ISSUE DAYS
7
with at least 1 issue
PHOTOS
264
captured + tagged
FILTER31 of 31
147 workers12 photosNo issues
AI · NARRATIVE
writing

  • Level 1 · Court C2 gallery deck pour completed at 16:47
  • Cement delivery (200 bags) confirmed at 14:32
  • Central Court C4 ring-beam rebar tying — 70% complete
  • Shopfront fit-out crew started Ground · Akbari arcade run
Civil: 78Steel: 22MEP: 18Finishes: 12Other: 171,176 hours worked
152 workers9 photos1 issue
AI · NARRATIVE
writing

  • Level 1 · C2 bay shuttering completed
  • Rebar delivery 12 tons received
  • Gate portals masonry — final darwaza topped out
  • MEP first fix continued Ground · south wing
Civil: 81Steel: 24MEP: 18Finishes: 14Other: 151,216 hours worked
88 workers5 photosNo issues
AI · NARRATIVE
writing

  • Reduced crew (Sunday)
  • Equipment maintenance on Tower Crane Main
  • Lay-down yard reorganisation
Civil: 48Steel: 12MEP: 10Finishes: 8Other: 10704 hours worked
100 workers3 photos2 issues
AI · NARRATIVE
writing

  • Site safety audit
  • Yard reorganisation
Civil: 52Steel: 16MEP: 13Finishes: 9Other: 10800 hours worked
143 workers10 photosNo issuesHot
AI · NARRATIVE
writing

  • Site engineer walkthrough — no findings
  • Level 1 gallery shuttering work
  • Cement delivery received
Civil: 74Steel: 23MEP: 19Finishes: 13Other: 141,144 hours worked
152 workers11 photosNo issuesHot
AI · NARRATIVE
writing

  • Drone capture flown for weekly progress
  • Subcontractor onboarding meeting
  • Central Court C4 rebar tying continued
Civil: 79Steel: 24MEP: 20Finishes: 14Other: 151,216 hours worked